Planning · 3 min read

Knockdown-rebuild in Sydney: the site preparation checklist

Step-by-step checklist from approval to slab-ready site: disconnections, asbestos, demolition, trees, excavation and handing over to your builder.

Excavator with grab sorting timber framing and debris during a residential demolition in Sydney

The short answer

A smooth knockdown-rebuild comes down to sequence: approval → disconnections → asbestos removal → demolition → site cut and levelling → handover to your builder. Most delays happen when one of these steps is left too late.

1. Approval

Your new home and the demolition are usually approved together, either by CDC or DA. Read the demolition conditions early, they set working hours, notification requirements, tree protection and waste rules.

2. Service disconnections

  • Electricity: abolishment requested through your electricity distributor
  • Gas: meter removal and disconnection through your gas distributor
  • Water and sewer: capped by a licensed plumber
  • Telecommunications: NBN and other lines removed if required

Disconnections can take weeks, so lodge them as soon as your approval is issued.

3. Asbestos

Any home built before 2004 needs asbestos identified before demolition. Licensed removal and a clearance certificate come next, the demolition can't start until this is done.

4. Demolition

The house, outbuildings, driveways, paths and pools are removed as your approval and builder require. Ask your demolition contractor:

  • Are footings and slabs being removed?
  • Are trees being removed or protected?
  • Is the driveway and crossover staying for construction access?
  • Is the site being levelled and compacted at the end?

5. Site cut and levelling

Most new homes need a site cut to the levels on the engineering plans, especially on sloping Sydney blocks. If your demolition contractor also does excavation, this can follow straight on without a gap.

6. Handover to your builder

A good handover is a clean, level site, spoil removed, temporary fencing in place, and photos of the finished site.

Why one contractor helps

Top Tier SiteWorks handles demolition, excavation, retaining walls and concreting. Using one team for the whole site-prep stage avoids finger-pointing between trades and keeps your builder's start date safe.

Frequently asked questions

How long does site preparation take for a knockdown-rebuild?

The physical work, demolition and site cut, is often one to three weeks for a typical house. Approvals and disconnections usually take longer, so start them early.

Should the demolisher remove the slab?

Usually yes for a new home, but check with your builder. Some designs reuse parts of the existing slab or need footings left for a specific reason.

About the authors. Frank, Joe and George own Top Tier SiteWorks. Together they’ve spent 15+ years on Sydney demolition, excavation and concrete jobs. This guide is general information. Always check the conditions on your own approval with your council or certifier.

Related: Domestic DemolitionExcavationConcreting